Steel Building Lead Times
We work exceptional hard to deliver our steel buildings within customer time frames. As a standard were able to provide steel building kit within 2-4 weeks. That’s based on approval being received by return each time we issue a document.
Our process of order is as follows:
- Quotation and dialog about the quotation and specifics regarding the clients building
- Pre order check to confirm building details have been interpreted correctly
- Once the pre order is approved, we begin General Arrangement drawings
- The General Arrangement drawings will show exact door positions and sizes. Internal dimensions, steelwork layouts, base plans etc.
- Once the General Arrangements have been approved, we agree a delivery date and begin manufacturing process.
- Confirm with customer 2-3 days prior to delivery date on being, to ensure all is in order and ready to take delivery.
- After sales support if required.